Q. 1: At what time is the order placed by Client 1 completely served? A) 10:17 B) 10:10 C) 10:15 D) 10:20
Q. 3: Suppose the employees are allowed to process multiple orders at a time, but the preference would be to finish orders of clients who placed their orders earlier.
At what time is the order placed by Client 2 completely served?
A) 10:10 B) 10:12 C) 10:15 D) 10:17
Q. 4: Suppose the employees are allowed to process multiple orders at a time, but the preference would be to finish orders of clients who placed their orders earlier.
Also assume that the fourth client came in only at 10:35. Between 10:00 and 10:30, for how many minutes is exactly one of the employees idle?
A) 7 B) 10 C) 15 D) 23
QNo:-1, Correct Answer:- B
Explanation:- As the item which take the maximum time is burger, client 1 will be completely served by 10.00
+ 10 minutes = 10.10
QNo:- 2 ,Correct Answer:- C
Explanation:- The time taken for the different clients are Client 1 – 10.00 – 10.10 (burger)
Client 2 – 10.10 – 10.15 (fries)
Client 3 – 10.15 – 10.25 (burger)
QNo:- 3 ,Correct Answer:- A
Explanation:- When they are allowed to process multiple orders, the time taken would be
Client 1 – 10.00 – 10.10 (Anish)
Client 2 – 10.05 – 10.10 (Bani)
The second client can be served by 10.10
QNo:- 4 ,Correct Answer:- B
Explanation:- The time for which exactly one employee would be free would be
10.02 – 10.05 – (Bani) – 3 Minutes.
10.10 – 10.17 (Anish/Bani) – 7 minutes (depending on who prepares the order for client 3. After 10.17 both of them would be free.
∴ One of them would be free for 3 + 7 = 10 minutes.
Verbal Ability : | Q.01- Q.06 | Q.07- Q.12 | Q.13- Q.18 | Q.19- Q.21 | Q.22- Q.24 | Q.25- Q.29 | Q.30 – Q.34 |
Logical Reasoning : | Q.01- Q.04 | Q.05- Q.08 | Q.09- Q.12 | Q.13- Q.16 | Q.17- Q.20 | Q.21- Q.24 | Q.25 – Q.28 | Q.29 – Q.32 |
Quantitative Aptitude: | Q.01- Q.05 | Q.06- Q.10 | Q.11- Q.15 | Q.16- Q.20 | Q.21- Q.25 | Q.26- Q.30 | Q.31 – Q.34 |
Inspiring Education… Assuring Success!!
Ⓒ 2020 – All Rights Are Reserved